Project scope includes upgrading existing facility PLC, SIS, and HMI systems. Our Automation & Controls team provided project management services, procurement, programming, graphics development, testing, and onsite deployment. To eliminate the need for facility downtime, a detailed cutover procedure was developed and tested prior to implementation. The new systems were cutover successfully without interruption of facility production.
Project Summary
Client: Occidental Petroleum (OXY)
Location: Denver, Colorado USA
Central Oil Stabilizing Facility: 250,000 bbl./Day
Year: 2018
Project Scope Includes
- Functional Design Specification
- As-built Control Narratives, Cause and Effect Diagrams
- PLC and SIS panel design drawings
- Programming and Configuration
- Cutover Procedure Development
- Factory Acceptance Testing (FAT)
- Site Acceptance Testing (SAT) and Commissioning
- Operator Training and Startup Support